Project scope and timeline

DESIGN_latest_images_v2

Project scope

The Monash Children’s Hospital service profile will include:

  • 96 in-patient acute beds
  • 10 paediatric intensive care beds
  • 64 Monash Newborn cots
  • 20 Early in Life Mental Health Service beds
  • 8 neurodevelopmental psychiatry beds
  • 20 same-day beds
  • 12 oncology same-day beds
  • 4 operating theatres incorporating a dedicated endoscopy suite
  • sleep study and neurodiagnostic beds
  • 3 imaging modalities (MRI, Ultrasound and X-Ray)
  • outpatient consulting rooms
  • Monash University education and research precinct clinical skills centre
  • 2 simulation centres
  • allied health therapy spaces
  • dedicated central sterilising services department
  • partnerships with Starlight Foundation, Ronald McDonald House, Kidsafe, Hoyts, Radio Lollipop, and Healesville Sanctuary
  • the Monash Children’s Hospital School

The Monash Children’s Hospital vital statistics

  • One of only two tertiary paediatric facilities for Victorian children and their families
  • Purpose-built paediatric facility where clinical services will be delivered in a child and family-friendly environment
  • 230 beds
  • One of the biggest capital infrastructure projects underway to date for Monash Health


Interesting construction facts

  • 14,000 cubic metres of concrete will be used in construction
  • 1500 tonnes of reinforcement
  • 35000m2 of plasterboard will be used
  • 1000 doors will be installed
  • 35000m2 of floor finishes including vinyl and carpet
  • 35000 cubic metres of dirt will be removed
  • Two-year construction program
  • Two cranes on site

 

Construction timeline 

In December 2013, the Victorian State Government announced the appointment of Lend Lease Building as the managing contractor for the construction of the new Monash Children’s Hospital.

The construction of the new hospital will work to the following schedule: 

  • June 2014: Helipad relocated from site
  • July 2014: Construction works commence on site
  • September 2014: Commencement of concrete structure
  • October 2014: Erection of first crane
  • November 2014: Erection of second crane
  • August 2015: Concrete structure complete
  • October 2015: Façade envelope complete
  • December 2016: Building works complete